Assessment Year | 2004 |
---|---|
Principal Product | Lemon and Lime Juice from Concentrate |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 33 |
Plant Area |
107,674
ft2
|
Annual Production | 2,471,000
pieces
|
Production Hrs. Annual | 4,972
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,126 | 1,918,600 |
kWh
|
$0.082 |
Electricity Demand | $60,091 | 6,413 |
kW-mo/yr
|
$9.37 |
Electricity Fees | $432 | - |
|
- |
Natural Gas | $48,920 | 5,093 |
MMBtu
|
$9.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,881 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,956 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $7,681 | - | - | - | $7,681 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $5,671 | $133 |
$4,444
54,195
kWh
|
$1,227
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,691 | $736 |
$2,895
35,301
kWh
|
$796
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $925 | $401 |
$925
11,282
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,416 | $883 |
$470
5,729
kWh
|
$75
-
kW-mo/yr
|
$871 | |
06 | 2.4224: Upgrade controls on compressors | $25,497 | $15,000 |
$22,414
273,342
kWh
|
$3,083
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $44,881 | $17,153 |
$31,148
379,849
kWh
|
$5,181
-
kW-mo/yr
|
$8,552 | ||
TOTAL IMPLEMENTED | $43,956 | $16,752 |
$30,223
368,567
kWh
|
$5,181
-
kW-mo/yr
|
$8,552 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs