ITAC Assessment: SU0192
ITAC logo
ITAC Assessment: SU0192
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Printed Tags and Labels
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 154
Plant Area 67,500
ft2
Annual Production 703,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,887 1,719,900
kWh
Electricity Demand $24,098 4,430
kW-mo/yr
Natural Gas $16,308 3,031
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $338,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $335,310

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 4.431: Train operators for maximum operating efficiency $65,154 $9,000 - - $65,154
02 2.7135: Install occupancy sensors $3,355 $1,049 $3,355
67,092
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $1,106 $491 $780
15,604
kWh
$326
-
kW-mo/yr
-
04 4.132: Purchase new equipment to reduce material use / cost $217,181 $187,500 - - $217,181
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $51,637 $45,000 - - $51,637
06 2.7111: Reduce illumination to minimum necessary levels $232 $250 $150
2,995
kWh
$82
-
kW-mo/yr
-
TOTAL RECOMMENDED $338,665 $243,290 $4,285
85,691
kWh
$408
-
kW-mo/yr
$333,972
TOTAL IMPLEMENTED $335,310 $242,241 $930
18,599
kWh
$408
-
kW-mo/yr
$333,972
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs