Assessment Year | 2004 |
---|---|
Principal Product | Dairy Products |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $100 M to 500M |
# of Employees | 130 |
Plant Area |
110,300
ft2
|
Annual Production | 106,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $134,594 | 7,491,750 |
kWh
|
$0.018 |
Electricity Demand | $2,990 | 14,699 |
kW-mo/yr
|
$0.20 |
Electricity Fees | $7,130 | - |
|
- |
Natural Gas | $38,145 | 3,889 |
MMBtu
|
$9.81 |
Fuel Oil #6 | $304,090 | 52,157 |
MMBtu
|
$5.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,124 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,488 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,017 | - |
$998
49,920
kWh
|
$19
-
kW-mo/yr
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $382 | $328 |
$375
18,720
kWh
|
$7
-
kW-mo/yr
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $19,058 | $25,000 | - | - |
$19,058
-
MMBtu
|
- | |
04 | 2.2691: Shut off cooling if cold outside air will cool process | $19,254 | $38,185 |
$18,708
935,424
kWh
|
$546
-
kW-mo/yr
|
- | - | |
05 | 2.7132: Install timers on light switches in little used areas | $1,413 | $2,856 |
$1,413
70,668
kWh
|
- | - | - | |
06 | 2.4112: Install soft-start to eliminate nuisance trips | $3,000 | $7,400 | - | - | - | $3,000 | |
TOTAL RECOMMENDED | $44,124 | $73,769 |
$21,494
1,074,732
kWh
|
$572
-
kW-mo/yr
|
$19,058
-
MMBtu
|
$3,000 | ||
TOTAL IMPLEMENTED | $21,488 | $27,856 |
$2,411
120,588
kWh
|
$19
-
kW-mo/yr
|
$19,058
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs