ITAC Assessment: SU0191
ITAC logo
ITAC Assessment: SU0191
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Dairy Products
NAICS 311511: Fluid Milk Manufacturing
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $100
M
to 500
M
# of Employees 130
Plant Area 110,300
ft2
Annual Production 106,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,594 7,491,750
kWh
Electricity Demand $2,990 14,699
kW-mo/yr
Electricity Fees $7,130 -
Natural Gas $38,145 3,889
MMBtu
Fuel Oil #6 $304,090 52,157
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,124 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,488

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,017 - $998
49,920
kWh
$19
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $382 $328 $375
18,720
kWh
$7
-
kW-mo/yr
- -
03 2.2414: Use waste heat from hot flue gases to preheat $19,058 $25,000 - - $19,058
-
MMBtu
-
04 2.2691: Shut off cooling if cold outside air will cool process $19,254 $38,185 $18,708
935,424
kWh
$546
-
kW-mo/yr
- -
05 2.7132: Install timers on light switches in little used areas $1,413 $2,856 $1,413
70,668
kWh
- - -
06 2.4112: Install soft-start to eliminate nuisance trips $3,000 $7,400 - - - $3,000
TOTAL RECOMMENDED $44,124 $73,769 $21,494
1,074,732
kWh
$572
-
kW-mo/yr
$19,058
-
MMBtu
$3,000
TOTAL IMPLEMENTED $21,488 $27,856 $2,411
120,588
kWh
$19
-
kW-mo/yr
$19,058
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs