ITAC Assessment: SU0188
ITAC logo
ITAC Assessment: SU0188
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Gas Fired Low Intensity Infrared Heaters
NAICS 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 100,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 1,920
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,838 690,560
kWh
Electricity Demand $38,754 2,589
kW-mo/yr
Electricity Fees $17,910 -
Natural Gas $43,679 6,692
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,476 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,621

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 4.731: Advertise product or service $10,418 - - - $10,418
02 2.8123: Pay utility bills on time $1,203 - - - $1,203
03 2.4231: Reduce the pressure of compressed air to the minimum required $883 - $344
5,729
kWh
$539
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $548 $184 $214
3,571
kWh
$334
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $5,424 $34,382 $2,909
48,480
kWh
$2,515
-
kW-mo/yr
-
TOTAL RECOMMENDED $18,476 $34,566 $3,467
57,780
kWh
$3,388
-
kW-mo/yr
$11,621
TOTAL IMPLEMENTED $11,621 - - - $11,621
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs