| Assessment Year | 2003 |
|---|---|
| Principal Product | Automotive engine blocks and heads |
| NAICS | 331524: Aluminum Foundries (except Die-Casting) |
| SIC | 3400: |
| Sales Range | $100 M to 500M |
| # of Employees | 577 |
| Plant Area |
862,107
ft2
|
| Annual Production | 1,141,283
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $928,893 | 107,448,400 |
kWh
|
$0.009 |
| Electricity Demand | $1,170,402 | 185,265 |
kW-mo/yr
|
$6.32 |
| Natural Gas | $5,075,568 | 1,173,722 |
MMBtu
|
$4.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,986,551 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,336,834 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.3128: Utilize other methods to remove contaminants | $446,941 | $142,000 |
$(-187.0)
(-9,360)
kWh
|
$105,804
-
MMBtu
|
$389,124
-
lb
|
$(-47,800.0) | |
| 02 | 2.2437: Recover waste heat from equipment | $158,477 | $3,600 | - |
$158,477
-
MMBtu
|
- | - | |
| 03 | 2.2437: Recover waste heat from equipment | $1,336,834 | $875,536 | - |
$1,336,834
-
MMBtu
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $16,605 | $34,047 | - |
$16,605
-
MMBtu
|
- | - | |
| 05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $8,492 | $4,200 | - |
$8,492
-
MMBtu
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,587 | - |
$6,587
765,996
kWh
|
- | - | - | |
| 07 | 2.2511: Insulate bare equipment | $6,473 | $6,375 | - |
$6,473
-
MMBtu
|
- | - | |
| 08 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $4,145 | $12,781 | - |
$4,145
-
MMBtu
|
- | - | |
| 09 | 2.2511: Insulate bare equipment | $1,997 | $3,315 | - |
$1,997
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $1,986,551 | $1,081,854 |
$6,400
756,636
kWh
|
$1,638,827
-
MMBtu
|
$389,124
-
lb
|
$(-47,800.0) | ||
| TOTAL IMPLEMENTED | $1,336,834 | $875,536 | - |
$1,336,834
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs