Assessment Year | 2003 |
---|---|
Principal Product | Metal Finishing |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
32,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | New York |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,651 | 780,000 |
kWh
|
$0.051 |
Electricity Demand | $42,521 | 3,210 |
kW-mo/yr
|
$13.25 |
Electricity Fees | $13,179 | - |
|
- |
Natural Gas | $47,036 | 9,045 |
MMBtu
|
$5.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,357 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,357 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.5145: Recover and reuse spent acid baths | $21,400 | $1,800 | - | - | - |
$21,400
-
gal
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,081 | $8,364 |
$1,541
22,658
kWh
|
$1,540
-
kW-mo/yr
|
- | - | |
03 | 2.2511: Insulate bare equipment | $2,283 | $995 | - | - |
$2,283
-
MMBtu
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $1,534 | $327 |
$1,534
22,556
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,059 | - |
$542
7,969
kWh
|
$517
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $29,357 | $11,486 |
$3,617
53,183
kWh
|
$2,057
-
kW-mo/yr
|
$2,283
-
MMBtu
|
$21,400
-
gal
|
||
TOTAL IMPLEMENTED | $29,357 | $11,486 |
$3,617
53,183
kWh
|
$2,057
-
kW-mo/yr
|
$2,283
-
MMBtu
|
$21,400
-
gal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs