Assessment Year | 2002 |
---|---|
Principal Product | Brake controls and related components for railroad freight cars |
NAICS |
n/a
|
SIC | 3743: Railroad Equipment |
Sales Range | $50 M to 100M |
# of Employees | 261 |
Plant Area |
258,000
ft2
|
Annual Production | 12,400
pieces
|
Production Hrs. Annual | 3,840
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $481,747 | 6,395,540 |
kWh
|
$0.075 |
Electricity Demand | $79,229 | 14,458 |
kW-mo/yr
|
$5.48 |
Electricity Fees | $8,470 | - |
|
- |
Natural Gas | $262,636 | 32,985 |
MMBtu
|
$7.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,610 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,161 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $14,024 | $6,613 | - | - | - |
$14,024
-
MMBtu
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,420 | $89 |
$11,420
163,142
kWh
|
- | - | - | - | |
03 | 2.3212: Optimize plant power factor | $8,470 | $23,250 | - | - | $8,470 | - | - | |
04 | 2.2135: Repair and eliminate steam leaks | $4,103 | $178 | - | - | - |
$4,103
-
MMBtu
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $4,031 | $706 |
$2,707
38,667
kWh
|
$1,324
-
kW-mo/yr
|
- | - | - | |
06 | 2.2514: Cover open tanks | $2,938 | $1,769 | - | - | - |
$2,938
-
MMBtu
|
- | |
07 | 2.7135: Install occupancy sensors | $1,453 | $299 |
$1,134
16,195
kWh
|
$319
-
kW-mo/yr
|
- | - | - | |
08 | 2.2135: Repair and eliminate steam leaks | $1,197 | $22 | - | - | - |
$614
-
MMBtu
|
$583
-
Tgal
|
|
09 | 2.2511: Insulate bare equipment | $686 | $1,106 | - | - | - |
$686
-
MMBtu
|
- | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $288 | - |
$231
3,302
kWh
|
$57
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $48,610 | $34,032 |
$15,492
221,306
kWh
|
$1,700
-
kW-mo/yr
|
$8,470 |
$22,365
-
MMBtu
|
$583
-
Tgal
|
||
TOTAL IMPLEMENTED | $13,161 | $388 |
$12,785
182,639
kWh
|
$376
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs