ITAC Assessment: SU0127
ITAC logo
ITAC Assessment: SU0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Electronic Controls
NAICS
n/a
SIC 3625: Relays and Industrial Controls
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 65,000
ft2
Annual Production 1,600,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,384 722,132
kWh
Natural Gas $22,515 2,542
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,414 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $115

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Ancillary Material Cost Savings
01 3.6192: Use a less expensive method of waste removal $4,500 - - $4,500
02 2.2437: Recover waste heat from equipment $1,022 $416 $1,022
14,602
kWh
-
03 2.2511: Insulate bare equipment $781 $125 $781
11,160
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $574 $3,275 $574
8,207
kWh
-
05 2.7111: Reduce illumination to minimum necessary levels $377 - $377
5,382
kWh
-
06 2.7145: Install skylights $115 $697 $115
1,649
kWh
-
07 2.4221: Install compressor air intakes in coolest locations $45 $158 $45
483
kWh
-
TOTAL RECOMMENDED $7,414 $4,671 $2,914
41,483
kWh
$4,500
TOTAL IMPLEMENTED $115 $697 $115
1,649
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs