| Assessment Year | 2001 |
|---|---|
| Principal Product | Ceramic Dinnerware |
| NAICS |
n/a
|
| SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 450 |
| Plant Area |
660,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $378,388 | 13,708,963 |
kWh
|
$0.028 |
| Electricity Demand | $336,830 | 31,204 |
kW-mo/yr
|
$10.79 |
| Electricity Fees | $51,608 | - |
|
- |
| Natural Gas | $1,710,849 | 422,656 |
MMBtu
|
$4.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8112: Combine utility meters | $5,085 | - | - | - | $5,085 | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,180 | $2,241 |
$13,180
183,763
kWh
|
- | - | - | |
| 03 | 3.4151: Minimize water usage | $51,680 | $1,605 | - | - | - |
$51,680
-
Tgal
|
|
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $2,023 | $90 |
$1,257
41,911
kWh
|
$766
-
kW-mo/yr
|
- | - | |
| 05 | 2.7122: Disconnect ballasts | $65 | - |
$22
879
kWh
|
$43
-
kW-mo/yr
|
- | - | |
| 06 | 2.3212: Optimize plant power factor | $1,526 | $3,780 | - | - | $1,526 | - | |
| TOTAL RECOMMENDED | $73,559 | $7,716 |
$14,459
226,553
kWh
|
$809
-
kW-mo/yr
|
$6,611 |
$51,680
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs