ITAC Assessment: SU0109
ITAC logo
ITAC Assessment: SU0109
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product cable system products
NAICS
n/a
SIC 3678: Electronic Connectors
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 112,000
ft2
Annual Production 0
units
Production Hrs. Annual 3,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $189,878 4,520,894
kWh
Electricity Demand $109,148 9,816
kW-mo/yr
Electricity Fees $25,326 -
Natural Gas $20,229 5,295
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,451 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,225

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,244 - $1,244
29,617
kWh
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $28 - $28
655
kWh
- - -
03 2.2511: Insulate bare equipment $1,123 $213 - - - $1,123
-
MMBtu
04 2.7111: Reduce illumination to minimum necessary levels $1,246 $662 $605
14,400
kWh
$641
-
kW-mo/yr
- -
05 2.4322: Use or replace with energy efficient substitutes $3,828 $30 $2,505
59,640
kWh
$1,323
-
kW-mo/yr
- -
06 2.8114: Change rate schedules or other changes in utility service $982 - - - $982 -
TOTAL RECOMMENDED $8,451 $905 $4,382
104,312
kWh
$1,964
-
kW-mo/yr
$982 $1,123
-
MMBtu
TOTAL IMPLEMENTED $6,225 $905 $3,138
74,695
kWh
$1,964
-
kW-mo/yr
- $1,123
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs