ITAC Assessment: MZ0356
ITAC logo
ITAC Assessment: MZ0356
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product underbody welded assemblies
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 470,000
ft2
Annual Production 298,898
pieces
Production Hrs. Annual 4,704
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,136,953 15,550,660
kWh
Electricity Demand $108,754 33,440
kW-mo/yr
Natural Gas $194,004 15,923
MMBtu
Waste Disposal Costs
Water Usage $8,027 1,538
Tgal
Water Disposal $16,727 1,538
Tgal
TOTAL YEARLY COSTS $1,464,465
RECOMMENDED SAVINGS* $735,794 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,756

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
01 2.7135: Install occupancy sensors $519 $415 $519
7,113
kWh
- - - -
02 2.4239: Eliminate or reduce compressed air usage $10,731 $440 $10,731
146,994
kWh
- - - -
03 2.2437: Recover waste heat from equipment $29,176 $63,400 - $29,176
-
MMBtu
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,117 $14,802 $11,117
152,262
kWh
- - - -
05 2.7221: Lower temperature during the winter season and vice-versa $6,120 $2,680 $3,967
54,356
kWh
$2,153
-
MMBtu
- - -
06 2.9114: Use solar heat to make electricty $525,252 $3,450,533 $525,252
7,236,330
kWh
- - - -
07 2.7425: Clean or color roof to reduce solar load $135,000 $306,035 - - - - $135,000
08 3.4116: Meter recycled water (to reduce sewer charges) $7,202 $7,540 - - - $7,202
-
Tgal
-
09 3.4159: Replace treated water with well / surface water $10,677 $100,000 - - $3,448
-
Tgal
$7,229
-
Tgal
-
TOTAL RECOMMENDED $735,794 $3,945,845 $551,586
7,597,055
kWh
$31,329
-
MMBtu
$3,448
-
Tgal
$14,431
-
Tgal
$135,000
TOTAL IMPLEMENTED $17,756 $17,897 $15,603
213,731
kWh
$2,153
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs