ITAC Assessment: SU0107
ITAC logo
ITAC Assessment: SU0107
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product malt beverages
NAICS
n/a
SIC 2082: Malt Beverages
Sales Range $500
k
to 1
M
# of Employees 6
Plant Area 9,000
ft2
Annual Production 3,500
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,991 181,707
kWh
Electricity Demand $6,965 820
kW-mo/yr
Electricity Fees $570 -
Natural Gas $4,229 461
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,619 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,619

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,945 $750 $3,945
79,872
kWh
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $410 $390 $410
9,360
kWh
-
03 2.2511: Insulate bare equipment $170 $59 $170
2,245
kWh
-
04 2.2136: Install / repair insulation on steam lines $50 $20 $50
668
kWh
-
05 2.8123: Pay utility bills on time $44 - - $44
TOTAL RECOMMENDED $4,619 $1,219 $4,575
92,145
kWh
$44
TOTAL IMPLEMENTED $4,619 $1,219 $4,575
92,145
kWh
$44
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs