| Assessment Year | 1986 |
|---|---|
| Principal Product | CONFECTIONARY CHOCOLATE |
| NAICS |
n/a
|
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
n/a
|
| Annual Production | 500,000
lb
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $101,661 | 757,034 |
kWh
|
$0.13 |
| Natural Gas | $17,782 | 1,922 |
MMBtu
|
$9.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,322 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,322 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $381 | $537 | - |
$381
-
MMBtu
|
|
| 02 | 2.1123: Install automatic stack damper | $878 | $846 | - |
$878
-
MMBtu
|
|
| 03 | 2.6121: Reduce hot water temperature to the minimum required | $66 | - | - |
$66
-
MMBtu
|
|
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $944 | $900 |
$1,326
9,965
kWh
|
$(-382.0)
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $122 | $30 |
$122
879
kWh
|
- | |
| 06 | 2.7226: Use computer programs to optimize hvac performance | $27,027 | $30,000 |
$27,027
751,759
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $169 | $150 |
$169
1,172
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $735 | $278 |
$735
5,569
kWh
|
- | |
| TOTAL RECOMMENDED | $30,322 | $32,741 |
$29,379
769,344
kWh
|
$943
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $30,322 | $32,741 |
$29,379
769,344
kWh
|
$943
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs