ITAC Assessment: ST0074
ITAC logo
ITAC Assessment: ST0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product CHINA & POTTERY
NAICS
n/a
SIC 3262: Vitreous China Table and Kitchen Articles
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area
n/a
Annual Production 400,000
pieces
Production Hrs. Annual 4,125
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $485,311 8,347,890
kWh
Natural Gas $893,001 172,898
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $146,596 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $133,150

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,553 - $6,553
112,837
kWh
-
02 2.2437: Recover waste heat from equipment $10,364 $6,000 - $10,364
-
MMBtu
03 2.2515: Use optimum thickness insulation $1,489 $1,500 - $1,489
-
MMBtu
04 2.4133: Use most efficient type of electric motors $1,008 $3,000 $1,008
17,292
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,074 $1,050 $2,074
35,756
kWh
-
06 2.2414: Use waste heat from hot flue gases to preheat $125,108 $160,000 - $125,108
-
MMBtu
TOTAL RECOMMENDED $146,596 $171,550 $9,635
165,885
kWh
$136,961
-
MMBtu
TOTAL IMPLEMENTED $133,150 $161,500 $6,553
112,837
kWh
$126,597
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs