Assessment Year | 1986 |
---|---|
Principal Product | ASSORTED METAL STAMPINGS |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $1 M to 5M |
# of Employees | 56 |
Plant Area |
n/a
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,485 | 1,007,034 |
kWh
|
$0.076 |
Natural Gas | $119,687 | 20,951 |
MMBtu
|
$5.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $130,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $117,925 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,163 | $300 |
$4,163
54,807
kWh
|
- | - | |
02 | 2.6121: Reduce hot water temperature to the minimum required | $246 | - |
$223
2,931
kWh
|
$23
-
MMBtu
|
- | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $264 | $1,000 |
$378
4,982
kWh
|
$(-114.0)
-
MMBtu
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $579 | $1,750 |
$579
7,620
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,224 | $1,700 |
$1,224
16,120
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,132 | $6,007 |
$12,132
159,730
kWh
|
- | - | |
07 | 2.7233: Use properly designed and sized hvac equipment | $112,028 | $82,000 | - |
$62,028
-
MMBtu
|
$50,000 | |
TOTAL RECOMMENDED | $130,636 | $92,757 |
$18,699
246,190
kWh
|
$61,937
-
MMBtu
|
$50,000 | ||
TOTAL IMPLEMENTED | $117,925 | $85,000 |
$5,988
78,840
kWh
|
$61,937
-
MMBtu
|
$50,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs