ITAC Assessment: ST0061
ITAC logo
ITAC Assessment: ST0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product MILITARY HARDWARE
NAICS
n/a
SIC 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,125
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,204 1,113,423
kWh
Natural Gas $24,315 3,608
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,028 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,324

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $4,711 $500 - $4,711
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $856 - $856
7,620
kWh
-
03 2.7492: Use proper thickness of insulation on building envelope $11,111 $19,028 - $11,111
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,593 $421 $1,593
14,068
kWh
-
05 2.1123: Install automatic stack damper $757 $1,410 - $757
-
MMBtu
TOTAL RECOMMENDED $19,028 $21,359 $2,449
21,688
kWh
$16,579
-
MMBtu
TOTAL IMPLEMENTED $6,324 $1,910 $856
7,620
kWh
$5,468
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs