ITAC Assessment: SJ0055
ITAC logo
ITAC Assessment: SJ0055
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Ground & Whole Bean Coffee
NAICS 311920: Coffee and Tea Manufacturing
SIC 2095: Roasted Coffee
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 75,000
ft2
Annual Production 71,000
lb
Production Hrs. Annual 3,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,788 427,895
kWh
Electricity Demand $45,615 1,858
kW-mo/yr
Natural Gas $78,549 3,752
MMBtu
TOTAL YEARLY COSTS $273,952
RECOMMENDED SAVINGS* $110,844 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $986 - $937
2,678
kWh
$49
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $868 - $735
2,100
kWh
$133
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $989 $7,310 - $989
-
kW-mo/yr
- -
04 2.9114: Use solar heat to make electricty $105,896 $509,829 $105,896
302,560
kWh
- - -
05 2.8112: Combine utility meters $2,104 - - - $2,104 -
06 2.3142: User battery storage for power quality issues $1 - - - - $1
TOTAL RECOMMENDED $110,844 $517,139 $107,568
307,338
kWh
$1,171
-
kW-mo/yr
$2,104 $1
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs