| Assessment Year | 2026 |
|---|---|
| Principal Product | Food species |
| NAICS | 311942: Spice and Extract Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 43 |
| Plant Area |
45,916
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,931 | 468,390 |
kWh
|
$0.15 |
| Electricity Demand | $20,094 | 1,653 |
kW-mo/yr
|
$12.16 |
| Natural Gas | $35,387 | 1,601 |
MMBtu
|
$22.11 |
| TOTAL YEARLY COSTS | $123,412 | |||
| RECOMMENDED SAVINGS* | $22,801 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,488 | $7,009 |
$1,075
7,410
kWh
|
$413
-
kW-mo/yr
|
- | |
| 02 | 2.2511: Insulate bare equipment | $2,105 | $1,983 | - | - |
$2,105
-
MMBtu
|
|
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $5,082 | $13 |
$238
1,638
kWh
|
- |
$4,844
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,357 | - |
$4,029
27,782
kWh
|
$328
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,383 | $15,726 |
$4,924
33,949
kWh
|
$1,459
-
kW-mo/yr
|
- | |
| 06 | 2.2443: Re-use or recycle hot or cold process exhaust air | $1,791 | $1,127 | - | - |
$1,791
-
MMBtu
|
|
| 07 | 2.7224: Reduce space conditioning during non-working hours | $1,595 | - |
$295
2,032
kWh
|
- |
$1,300
-
MMBtu
|
|
| TOTAL RECOMMENDED | $22,801 | $25,858 |
$10,561
72,811
kWh
|
$2,200
-
kW-mo/yr
|
$10,040
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs