ITAC Assessment: SJ0032
ITAC logo
ITAC Assessment: SJ0032
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Treated Wastewater, Struvite
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 19
Plant Area 220,000
ft2
Annual Production 796,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $357,176 2,864,610
kWh
Electricity Demand $316,650 5,783
kW-mo/yr
Natural Gas $52,814 4,174
MMBtu
TOTAL YEARLY COSTS $726,640
RECOMMENDED SAVINGS* $138,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.1336: Install equipment to utilize waste fuel $129,492 $206,023 $83,494
667,950
kWh
$45,998
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $400 $297 - - $400
-
MMBtu
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $869 - $869
6,955
kWh
- - -
04 4.631: Install an uninteruptable power supply $5,400 $34,907 - - - $5,400
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,156 $2,349 $776
6,208
kWh
$1,380
-
kW-mo/yr
- -
06 2.6218: Turn off equipment when not in use $123 - $123
986
kWh
- - -
TOTAL RECOMMENDED $138,440 $243,576 $85,262
682,099
kWh
$47,378
-
kW-mo/yr
$400
-
MMBtu
$5,400
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs