| Assessment Year | 2025 |
|---|---|
| Principal Product | Treated Wastewater, Struvite |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 19 |
| Plant Area |
220,000
ft2
|
| Annual Production | 796,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $357,176 | 2,864,610 |
kWh
|
$0.12 |
| Electricity Demand | $316,650 | 5,783 |
kW-mo/yr
|
$54.76 |
| Natural Gas | $52,814 | 4,174 |
MMBtu
|
$12.65 |
| TOTAL YEARLY COSTS | $726,640 | |||
| RECOMMENDED SAVINGS* | $138,440 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,425 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1336: Install equipment to utilize waste fuel | $129,492 | $206,023 |
$83,494
667,950
kWh
|
$45,998
-
kW-mo/yr
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $400 | $297 | - | - |
$400
-
MMBtu
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $869 | - |
$869
6,955
kWh
|
- | - | - | |
| 04 | 4.631: Install an uninteruptable power supply | $5,400 | $34,907 | - | - | - | $5,400 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,156 | $2,349 |
$776
6,208
kWh
|
$1,380
-
kW-mo/yr
|
- | - | |
| 06 | 2.6218: Turn off equipment when not in use | $123 | - |
$123
986
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $138,440 | $243,576 |
$85,262
682,099
kWh
|
$47,378
-
kW-mo/yr
|
$400
-
MMBtu
|
$5,400 | ||
| TOTAL IMPLEMENTED | $3,425 | $2,646 |
$1,645
13,163
kWh
|
$1,380
-
kW-mo/yr
|
$400
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs