Assessment Year | 2024 |
---|---|
Principal Product | Machined Components; Weldments |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 52 |
Plant Area |
60,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $434,466 | 1,532,665 |
kWh
|
$0.28 |
Electricity Demand | $76,966 | 4,126 |
kW-mo/yr
|
$18.65 |
Natural Gas | $7,338 | 294 |
MMBtu
|
$24.96 |
TOTAL YEARLY COSTS | $518,770 | |||
RECOMMENDED SAVINGS* | $252,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $227,474 | $847,735 |
$215,894
761,609
kWh
|
$11,580
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $493 | $109 |
$493
1,738
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,040 | - |
$3,040
10,726
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,291 | $2,078 |
$930
3,282
kWh
|
$361
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $1,255 | $1,308 |
$1,065
3,757
kWh
|
$190
-
kW-mo/yr
|
- | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $4,438 | - |
$4,438
15,656
kWh
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,813 | $12,216 |
$9,188
32,412
kWh
|
$625
-
kW-mo/yr
|
- | |
08 | 2.7221: Lower temperature during the winter season and vice-versa | $4,528 | - | - | - |
$4,528
-
MMBtu
|
|
TOTAL RECOMMENDED | $252,332 | $863,446 |
$235,048
829,180
kWh
|
$12,756
-
kW-mo/yr
|
$4,528
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs