ITAC Assessment: SJ0018
ITAC logo
ITAC Assessment: SJ0018
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Cast ison and steel parts
NAICS 331513: Steel Foundries (except Investment)
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 70,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $166,213 1,584,152
kWh
Electricity Demand $79,988 22,576
kW-mo/yr
Natural Gas $90,375 5,453
MMBtu
TOTAL YEARLY COSTS $336,576
RECOMMENDED SAVINGS* $39,557 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,066 $11,290 $5,914
56,367
kWh
$1,152
-
kW-mo/yr
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,985 $11,774 $2,498
23,804
kWh
$487
-
kW-mo/yr
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,691 $4,253 $2,527
24,086
kWh
$164
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,283 $4,037 $714
6,808
kWh
$569
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,414 $69 $1,414
13,475
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,365 $3,762 $1,142
10,887
kWh
$223
-
kW-mo/yr
07 2.9114: Use solar heat to make electricty $22,753 $159,594 $22,753
216,691
kWh
-
TOTAL RECOMMENDED $39,557 $194,779 $36,962
352,118
kWh
$2,595
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs