Assessment Year | 2024 |
---|---|
Principal Product | Metal parts |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $1 M to 5M |
# of Employees | 184 |
Plant Area |
100,000
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $496,142 | 2,332,332 |
kWh
|
$0.21 |
Electricity Demand | $251,612 | 6,760 |
kW-mo/yr
|
$37.22 |
Natural Gas | $44,297 | 2,308 |
MMBtu
|
$19.19 |
LPG | $19,996 | 555 |
MMBtu
|
$36.02 |
TOTAL YEARLY COSTS | $812,047 | |||
RECOMMENDED SAVINGS* | $254,608 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $184,626 | $998,282 |
$171,503
806,222
kWh
|
$13,123
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,795 | - |
$1,645
7,333
kWh
|
$150
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,258 | $759 |
$1,258
5,913
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,517 | $17 | - | - | - | $2,517 | |
05 | 2.7135: Install occupancy sensors | $1,226 | $414 |
$826
3,884
kWh
|
$400
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $50,102 | $51,343 |
$33,055
155,391
kWh
|
$17,047
-
kW-mo/yr
|
- | - | |
07 | 2.8112: Combine utility meters | $6,947 | - | - | - | $6,947 | - | |
08 | 2.2514: Cover open tanks | $1,257 | - |
$1,257
5,907
kWh
|
- | - | - | |
09 | 2.6241: Reduce temperature of process equipment when on standby | $4,880 | - |
$4,880
22,492
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $254,608 | $1,050,815 |
$214,424
1,007,142
kWh
|
$30,720
-
kW-mo/yr
|
$6,947 | $2,517 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs