ITAC Assessment: SJ0016
ITAC logo
ITAC Assessment: SJ0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal parts
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 100,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 4,335
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $408,137 2,715,998
kWh
Electricity Demand $319,012 7,330
kW-mo/yr
Natural Gas $116,229 7,523
MMBtu
LPG $9,774 271
MMBtu
TOTAL YEARLY COSTS $853,152
RECOMMENDED SAVINGS* $323,063 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $285,219 $1,390,697 $264,378
1,759,338
kWh
$20,841
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,753 $7,435 $3,309
22,021
kWh
$3,444
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $1,156 $713 $645
4,290
kWh
$511
-
kW-mo/yr
- - -
04 2.7135: Install occupancy sensors $4,114 $1,066 $2,263
15,060
kWh
$1,851
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $319 $356 $177
1,179
kWh
$142
-
kW-mo/yr
- - -
06 2.6241: Reduce temperature of process equipment when on standby $467 - $467
3,109
kWh
- - - -
07 2.7135: Install occupancy sensors $464 $315 $258
1,714
kWh
$206
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $1,500 $987 $833
5,541
kWh
$667
-
kW-mo/yr
- - -
09 2.7135: Install occupancy sensors $541 $692 $300
1,998
kWh
$241
-
kW-mo/yr
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,999 $271 $1,999
13,303
kWh
- - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $140 - - - - - $140
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $33 $38 $33
220
kWh
- - - -
13 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $1,169 $6,473 - - - $1,169
-
MMBtu
-
14 2.7221: Lower temperature during the winter season and vice-versa $10,157 - - - - $10,157
-
MMBtu
-
15 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,627 $9,934 $3,916
26,059
kWh
$711
-
kW-mo/yr
- - -
16 2.8112: Combine utility meters $4,405 - - - $4,405 - -
TOTAL RECOMMENDED $323,063 $1,418,977 $278,578
1,853,832
kWh
$28,614
-
kW-mo/yr
$4,405 $11,326
-
MMBtu
$140
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs