Assessment Year | 2024 |
---|---|
Principal Product | Metal parts |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
100,000
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $408,137 | 2,715,998 |
kWh
|
$0.15 |
Electricity Demand | $319,012 | 7,330 |
kW-mo/yr
|
$43.52 |
Natural Gas | $116,229 | 7,523 |
MMBtu
|
$15.45 |
LPG | $9,774 | 271 |
MMBtu
|
$36.13 |
TOTAL YEARLY COSTS | $853,152 | |||
RECOMMENDED SAVINGS* | $323,063 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $285,219 | $1,390,697 |
$264,378
1,759,338
kWh
|
$20,841
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,753 | $7,435 |
$3,309
22,021
kWh
|
$3,444
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $1,156 | $713 |
$645
4,290
kWh
|
$511
-
kW-mo/yr
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $4,114 | $1,066 |
$2,263
15,060
kWh
|
$1,851
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $319 | $356 |
$177
1,179
kWh
|
$142
-
kW-mo/yr
|
- | - | - | |
06 | 2.6241: Reduce temperature of process equipment when on standby | $467 | - |
$467
3,109
kWh
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $464 | $315 |
$258
1,714
kWh
|
$206
-
kW-mo/yr
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $1,500 | $987 |
$833
5,541
kWh
|
$667
-
kW-mo/yr
|
- | - | - | |
09 | 2.7135: Install occupancy sensors | $541 | $692 |
$300
1,998
kWh
|
$241
-
kW-mo/yr
|
- | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,999 | $271 |
$1,999
13,303
kWh
|
- | - | - | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $140 | - | - | - | - | - | $140 | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $33 | $38 |
$33
220
kWh
|
- | - | - | - | |
13 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $1,169 | $6,473 | - | - | - |
$1,169
-
MMBtu
|
- | |
14 | 2.7221: Lower temperature during the winter season and vice-versa | $10,157 | - | - | - | - |
$10,157
-
MMBtu
|
- | |
15 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,627 | $9,934 |
$3,916
26,059
kWh
|
$711
-
kW-mo/yr
|
- | - | - | |
16 | 2.8112: Combine utility meters | $4,405 | - | - | - | $4,405 | - | - | |
TOTAL RECOMMENDED | $323,063 | $1,418,977 |
$278,578
1,853,832
kWh
|
$28,614
-
kW-mo/yr
|
$4,405 |
$11,326
-
MMBtu
|
$140 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs