ITAC Assessment: SJ0012
ITAC logo
ITAC Assessment: SJ0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product build-to-print composite parts
NAICS 335991: Carbon and Graphite Product Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 32,000
ft2
Annual Production 9,999
units
Production Hrs. Annual 2,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,336 957,362
kWh
Electricity Demand $76,578 4,206
kW-mo/yr
Natural Gas $2,461 122
MMBtu
TOTAL YEARLY COSTS $376,375
RECOMMENDED SAVINGS* $175,326 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,778

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6218: Turn off equipment when not in use $26 - $26
82
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,374 - $1,017
3,273
kWh
$357
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $215 - $215
690
kWh
-
04 2.9114: Use solar heat to make electricty $151,265 $402,860 $142,949
460,264
kWh
$8,316
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $15,778 $22,286 $11,572
37,210
kWh
$4,206
-
kW-mo/yr
06 2.2212: Use minimum safe oven ventilation $157 $217 $116
373
kWh
$41
-
kW-mo/yr
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,511 $11,438 $6,511
20,694
kWh
-
TOTAL RECOMMENDED $175,326 $436,801 $162,406
522,586
kWh
$12,920
-
kW-mo/yr
TOTAL IMPLEMENTED $15,778 $22,286 $11,572
37,210
kWh
$4,206
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs