Assessment Year | 2024 |
---|---|
Principal Product | build-to-print composite parts |
NAICS | 335991: Carbon and Graphite Product Manufacturing |
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
32,000
ft2
|
Annual Production | 9,999
units
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $297,336 | 957,362 |
kWh
|
$0.31 |
Electricity Demand | $76,578 | 4,206 |
kW-mo/yr
|
$18.21 |
Natural Gas | $2,461 | 122 |
MMBtu
|
$20.17 |
TOTAL YEARLY COSTS | $376,375 | |||
RECOMMENDED SAVINGS* | $175,326 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,778 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $26 | - |
$26
82
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,374 | - |
$1,017
3,273
kWh
|
$357
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $215 | - |
$215
690
kWh
|
- | |
04 | 2.9114: Use solar heat to make electricty | $151,265 | $402,860 |
$142,949
460,264
kWh
|
$8,316
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,778 | $22,286 |
$11,572
37,210
kWh
|
$4,206
-
kW-mo/yr
|
|
06 | 2.2212: Use minimum safe oven ventilation | $157 | $217 |
$116
373
kWh
|
$41
-
kW-mo/yr
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,511 | $11,438 |
$6,511
20,694
kWh
|
- | |
TOTAL RECOMMENDED | $175,326 | $436,801 |
$162,406
522,586
kWh
|
$12,920
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $15,778 | $22,286 |
$11,572
37,210
kWh
|
$4,206
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs