ITAC Assessment: SJ0003
ITAC logo
ITAC Assessment: SJ0003
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Glassware
NAICS 327215: Glass Product Manufacturing Made of Purchased Glass
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 24,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,699 319,951
kWh
Natural Gas $3,838 174
MMBtu
TOTAL YEARLY COSTS $100,537
RECOMMENDED SAVINGS* $60,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.9114: Use solar heat to make electricty $57,369 $319,999 $49,582
164,055
kWh
$7,787
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $103 $218 $103
342
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,596 $5,020 $1,596
5,282
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $326 $20 $326
1,078
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $960 $2,889 $960
3,176
kWh
-
TOTAL RECOMMENDED $60,354 $328,146 $52,567
173,933
kWh
$7,787
TOTAL IMPLEMENTED $60,354 $328,146 $52,567
173,933
kWh
$7,787
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs