Assessment Year | 2023 |
---|---|
Principal Product | Machined metal parts |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
24,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,629 | 620,692 |
kWh
|
$0.27 |
Electricity Demand | $20,532 | 1,196 |
kW-mo/yr
|
$17.16 |
Natural Gas | $2,677 | 128 |
MMBtu
|
$20.88 |
TOTAL YEARLY COSTS | $193,838 | |||
RECOMMENDED SAVINGS* | $70,852 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $58,845 | $236,368 |
$55,516
224,218
kWh
|
$3,329
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,201 | - |
$2,045
8,258
kWh
|
$156
-
kW-mo/yr
|
- | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $6,541 | - | - | - | $6,541 | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $480 | - | - | - | - |
$480
-
MMBtu
|
|
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,785 | $1,200 |
$2,785
11,232
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $70,852 | $237,568 |
$60,346
243,708
kWh
|
$3,485
-
kW-mo/yr
|
$6,541 |
$480
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs