ITAC Assessment: SF0627
ITAC logo
ITAC Assessment: SF0627
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 80,000
ft2
Annual Production 60,000
units
Production Hrs. Annual 2,860
hrs
Location (State) Hawaii

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $407,439 1,157,511
kWh
Electricity Demand $129,426 5,178
kW-mo/yr
LPG $367,834 9,058
MMBtu
Waste Disposal Costs
Water Usage $75,315 11,352
Tgal
Water Disposal $78,135 11,352
Tgal
TOTAL YEARLY COSTS $1,058,149
RECOMMENDED SAVINGS* $517,035 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings By-product Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,292 - $8,732
24,808
kWh
- - - - - $(-1,440.0) -
02 2.2135: Repair and eliminate steam leaks $2,331 - - - - $3,411
-
MMBtu
- - $(-1,080.0) -
03 2.4231: Reduce the pressure of compressed air to the minimum required $4,552 $140 $4,147
11,780
kWh
$405
-
kW-mo/yr
- - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,465 $650 $17,465
49,617
kWh
- - - - - - -
05 2.2511: Insulate bare equipment $828 $98 - - - $828
-
MMBtu
- - - -
06 2.2511: Insulate bare equipment $772 $338 - - - $772
-
MMBtu
- - - -
07 2.2628: Utilize a less expensive cooling method $56,762 $75,338 $19,237
54,651
kWh
- - $32,886
-
MMBtu
$2,277
-
Tgal
$2,362
-
Tgal
- -
08 2.2123: Insulate feedwater tank $31,296 $45,008 - - - $24,163
-
MMBtu
$3,501
-
Tgal
$3,632
-
Tgal
- -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,796 $17,995 $6,796
19,306
kWh
- - - - - - -
10 2.2447: Heat water with exhaust heat $23,270 $67,410 - - - $23,270
-
MMBtu
- - - -
11 2.1241: Reduce excessive boiler blowdown $758 $3,995 - - - $585
-
MMBtu
$85
-
Tgal
$88
-
Tgal
- -
12 2.9121: Install wind powered electric generator $364,913 $212,152 $407,444
1,157,511
kWh
- $(-94,064.0) - - - $(-53,837.0) $105,370
TOTAL RECOMMENDED $517,035 $423,124 $463,821
1,317,673
kWh
$405
-
kW-mo/yr
$(-94,064.0) $85,915
-
MMBtu
$5,863
-
Tgal
$6,082
-
Tgal
$(-56,357.0) $105,370
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs