Assessment Year | 2024 |
---|---|
Principal Product | Beer |
NAICS | 312120: Breweries |
SIC | 2082: Malt Beverages |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
80,000
ft2
|
Annual Production | 60,000
units
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Hawaii |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $407,439 | 1,157,511 |
kWh
|
$0.35 | |
Electricity Demand | $129,426 | 5,178 |
kW-mo/yr
|
$25.00 | |
LPG | $367,834 | 9,058 |
MMBtu
|
$40.61 | |
Waste Disposal Costs | |||||
Water Usage | $75,315 | 11,352 |
Tgal
|
$6.63 | |
Water Disposal | $78,135 | 11,352 |
Tgal
|
$6.88 | |
TOTAL YEARLY COSTS | $1,058,149 | ||||
RECOMMENDED SAVINGS* | $517,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,292 | - |
$8,732
24,808
kWh
|
- | - | - | - | - | $(-1,440.0) | - | |
02 | 2.2135: Repair and eliminate steam leaks | $2,331 | - | - | - | - |
$3,411
-
MMBtu
|
- | - | $(-1,080.0) | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,552 | $140 |
$4,147
11,780
kWh
|
$405
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,465 | $650 |
$17,465
49,617
kWh
|
- | - | - | - | - | - | - | |
05 | 2.2511: Insulate bare equipment | $828 | $98 | - | - | - |
$828
-
MMBtu
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $772 | $338 | - | - | - |
$772
-
MMBtu
|
- | - | - | - | |
07 | 2.2628: Utilize a less expensive cooling method | $56,762 | $75,338 |
$19,237
54,651
kWh
|
- | - |
$32,886
-
MMBtu
|
$2,277
-
Tgal
|
$2,362
-
Tgal
|
- | - | |
08 | 2.2123: Insulate feedwater tank | $31,296 | $45,008 | - | - | - |
$24,163
-
MMBtu
|
$3,501
-
Tgal
|
$3,632
-
Tgal
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,796 | $17,995 |
$6,796
19,306
kWh
|
- | - | - | - | - | - | - | |
10 | 2.2447: Heat water with exhaust heat | $23,270 | $67,410 | - | - | - |
$23,270
-
MMBtu
|
- | - | - | - | |
11 | 2.1241: Reduce excessive boiler blowdown | $758 | $3,995 | - | - | - |
$585
-
MMBtu
|
$85
-
Tgal
|
$88
-
Tgal
|
- | - | |
12 | 2.9121: Install wind powered electric generator | $364,913 | $212,152 |
$407,444
1,157,511
kWh
|
- | $(-94,064.0) | - | - | - | $(-53,837.0) | $105,370 | |
TOTAL RECOMMENDED | $517,035 | $423,124 |
$463,821
1,317,673
kWh
|
$405
-
kW-mo/yr
|
$(-94,064.0) |
$85,915
-
MMBtu
|
$5,863
-
Tgal
|
$6,082
-
Tgal
|
$(-56,357.0) | $105,370 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs