Assessment Year | 2024 |
---|---|
Principal Product | Treated wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 75 |
Plant Area |
1,600,000
ft2
|
Annual Production | 5,110,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,541,562 | 6,803,344 |
kWh
|
$0.23 |
Electricity Demand | $535,088 | 12,010 |
kW-mo/yr
|
$44.55 |
Electricity Fees | $13,544 | - |
|
- |
Natural Gas | $62,561 | 3,507 |
MMBtu
|
$17.84 |
Other Gas | $1 | 53,340 |
MMBtu
|
$0.000 |
TOTAL YEARLY COSTS | $2,152,756 | |||
RECOMMENDED SAVINGS* | $2,615,351 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $101,612 | $3,840 |
$80,068
353,344
kWh
|
$21,544
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $39,113 | $24,553 |
$15,860
66,991
kWh
|
$7,831
-
kW-mo/yr
|
- | $15,880 | $(-458.0) | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $81,460 | $95,723 |
$64,192
283,284
kWh
|
$17,268
-
kW-mo/yr
|
- | - | - | |
04 | 2.4321: Upgrade obsolete equipment | $11,663 | $52,983 |
$9,204
40,619
kWh
|
$2,459
-
kW-mo/yr
|
- | - | - | |
05 | 2.4321: Upgrade obsolete equipment | $83,597 | $429,096 |
$60,856
268,562
kWh
|
$34,161
-
kW-mo/yr
|
- | $8,409 | $(-19,829.0) | |
06 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $1,786,404 | $4,187,700 |
$1,541,638
6,803,343
kWh
|
- | $420,507 | $(-175,741.0) | - | |
07 | 2.3141: Use battery storage for demand control | $511,502 | $6,765,825 | - |
$511,502
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $2,615,351 | $11,559,720 |
$1,771,818
7,816,143
kWh
|
$594,765
-
kW-mo/yr
|
$420,507 | $(-151,452.0) | $(-20,287.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs