| Assessment Year | 2017 |
|---|---|
| Principal Product | Museum |
| NAICS | 712110: Museums |
| SIC | 8422: Arboreta and Botanical or Zoological Gardens |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
168,104
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $535,774 | 8,401,519 |
kWh
|
$0.064 | |
| Electricity Demand | $115,830 | 14,961 |
kW-mo/yr
|
$7.74 | |
| Natural Gas | $27,272 | 4,111 |
MMBtu
|
$6.63 | |
| Waste Disposal Costs | |||||
| Water Usage | $102,731 | 20,134 |
Tgal
|
$5.10 | |
| TOTAL YEARLY COSTS | $781,607 | ||||
| RECOMMENDED SAVINGS* | $36,431 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7273: Install desiccant humidity control system | $17,595 | - |
$15,094
235,840
kWh
|
$2,501
-
kW-mo/yr
|
- | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $1,307 | - |
$1,121
17,520
kWh
|
$186
-
kW-mo/yr
|
- | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $1,869 | - |
$1,869
29,200
kWh
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,982 | - |
$1,700
26,561
kWh
|
$282
-
kW-mo/yr
|
- | |
| 05 | 2.2511: Insulate bare equipment | $12,478 | - |
$10,705
167,265
kWh
|
$1,773
-
kW-mo/yr
|
- | |
| 06 | 4.463: Modify facility to avoid excess maintenance costs | $1,200 | - | - | - | $1,200 | |
| TOTAL RECOMMENDED | $36,431 | - |
$30,489
476,386
kWh
|
$4,742
-
kW-mo/yr
|
$1,200 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs