| Assessment Year | 2023 |
|---|---|
| Principal Product | Concrete Products |
| NAICS | 327331: Concrete Block and Brick Manufacturing |
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $50 M to 100M |
| # of Employees | 108 |
| Plant Area |
973,473
ft2
|
| Annual Production | 35,000,000
units
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $731,758 | 5,334,236 |
kWh
|
$0.14 |
| Electricity Demand | $379,856 | 11,376 |
kW-mo/yr
|
$33.39 |
| Natural Gas | $867,081 | 62,633 |
MMBtu
|
$13.84 |
| Other Gas | $231,581 | 6,700 |
MMBtu
|
$34.56 |
| TOTAL YEARLY COSTS | $2,210,276 | |||
| RECOMMENDED SAVINGS* | $619,632 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $49,936 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $1,450 | $120 |
$1,089
7,917
kWh
|
$361
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,983 | $141 |
$1,462
10,630
kWh
|
$521
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,760 | $1,440 |
$7,760
56,441
kWh
|
- | - | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,008 | $7,651 |
$4,008
29,153
kWh
|
- | - | - | - | |
| 05 | 2.7134: Use photocell controls | $3,805 | $9,018 |
$3,805
27,673
kWh
|
- | - | - | - | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $31,772 | $124,644 | - | - |
$31,772
-
MMBtu
|
- | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $608 | $2,572 | - | - |
$608
-
MMBtu
|
- | - | |
| 08 | 2.1321: Replace fossil fuel equipment with electrical equipment | $568,246 | $3,565,479 |
$(-86,575.0)
(-629,635)
kWh
|
$(-40,080.0)
-
kW-mo/yr
|
- |
$231,581
-
MMBtu
|
$463,320 | |
| TOTAL RECOMMENDED | $619,632 | $3,711,065 |
$(-68,451.0)
(-497,821)
kWh
|
$(-39,198.0)
-
kW-mo/yr
|
$32,380
-
MMBtu
|
$231,581
-
MMBtu
|
$463,320 | ||
| TOTAL IMPLEMENTED | $49,936 | $145,466 |
$17,035
123,897
kWh
|
$521
-
kW-mo/yr
|
$32,380
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs