Assessment Year | 2024 |
---|---|
Principal Product | Rolled Steel |
NAICS | 331221: Rolled Steel Shape Manufacturing |
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
127,500
ft2
|
Annual Production | 50,000
ton
|
Production Hrs. Annual | 1,520
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $35,207 | 625,920 |
kWh
|
$0.056 | |
Electricity Demand | $43,394 | 4,950 |
kW-mo/yr
|
$8.77 | |
Electricity Fees | $8,030 | - |
|
- | |
Natural Gas | $380 | 1 |
MMBtu
|
$379.57 | |
Waste Disposal Costs | |||||
Water Usage | $15,635 | 500 |
Tgal
|
$31.27 | |
TOTAL YEARLY COSTS | $102,645 | ||||
RECOMMENDED SAVINGS* | $259,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $213,909 | $2,311,826 |
$213,909
3,819,815
kWh
|
- | - | - | |
02 | 2.7273: Install desiccant humidity control system | $23,487 | $32,590 |
$15
267
kWh
|
- | - | $23,472 | |
03 | 2.8121: Apply for tax-free status for energy purchases | $8,260 | $15,000 | - | - | $8,260 | - | |
04 | 2.3212: Optimize plant power factor | $6,940 | $16,200 | - |
$6,940
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,804 | $29,010 |
$2,695
50,815
kWh
|
$1,450
-
kW-mo/yr
|
$1,659 | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,360 | $10,180 |
$1,360
25,700
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $259,760 | $2,414,806 |
$217,979
3,896,597
kWh
|
$8,390
-
kW-mo/yr
|
$9,919 | $23,472 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs