| Assessment Year | 2005 |
|---|---|
| Principal Product | Asphalt |
| NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 415,778
ton
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $73,402 | 1,450,440 |
kWh
|
$0.051 |
| Electricity Demand | $48,178 | 5,863 |
kW-mo/yr
|
$8.22 |
| Electricity Fees | $14,757 | - |
|
- |
| Natural Gas | $1,536,393 | 903,761 |
MMBtu
|
$1.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $294,681 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1116: Improve combustion control capability | $122,911 | $75,000 | - |
$122,911
-
MMBtu
|
- | |
| 02 | 2.2136: Install / repair insulation on steam lines | $117,785 | $2,470 | - |
$117,785
-
MMBtu
|
- | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $49,464 | $16,000 | - | - | $49,464 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,676 | $1,110 |
$3,676
48,911
kWh
|
- | - | |
| 05 | 2.4314: Use synthetic lubricant | $845 | $780 |
$845
13,349
kWh
|
- | - | |
| TOTAL RECOMMENDED | $294,681 | $95,360 |
$4,521
62,260
kWh
|
$240,696
-
MMBtu
|
$49,464 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs