Assessment Year | 2022 |
---|---|
Principal Product | Anodizing, Plating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 24 |
Plant Area |
10,850
ft2
|
Annual Production | 20,000
units
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,180 | 507,648 |
kWh
|
$0.12 |
Electricity Demand | $16,539 | 1,893 |
kW-mo/yr
|
$8.74 |
Natural Gas | $54,628 | 3,302 |
MMBtu
|
$16.54 |
TOTAL YEARLY COSTS | $133,347 | |||
RECOMMENDED SAVINGS* | $40,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,446 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,621 | - |
$16,621
135,680
kWh
|
- | - | |
02 | 2.2514: Cover open tanks | $5,939 | $1,586 |
$5,939
48,482
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $303 | $85 |
$230
1,874
kWh
|
$73
-
kW-mo/yr
|
- | |
04 | 2.7224: Reduce space conditioning during non-working hours | $3,351 | $1,069 |
$378
3,090
kWh
|
- |
$2,973
-
MMBtu
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $822 | $334 |
$748
6,103
kWh
|
$74
-
kW-mo/yr
|
- | |
06 | 2.2515: Use optimum thickness insulation | $863 | $905 | - | - |
$863
-
MMBtu
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,539 | $5,175 |
$3,539
28,889
kWh
|
- | - | |
08 | 2.2622: Replace existing chiller with high efficiency model | $2,486 | $9,050 |
$2,255
18,404
kWh
|
$231
-
kW-mo/yr
|
- | |
09 | 2.9114: Use solar heat to make electricty | $6,111 | $42,120 |
$6,111
49,882
kWh
|
- | - | |
TOTAL RECOMMENDED | $40,035 | $60,324 |
$35,821
292,404
kWh
|
$378
-
kW-mo/yr
|
$3,836
-
MMBtu
|
||
TOTAL IMPLEMENTED | $24,446 | $11,443 |
$20,232
165,151
kWh
|
$378
-
kW-mo/yr
|
$3,836
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs