ITAC Assessment: SF0571
ITAC logo
ITAC Assessment: SF0571
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Sheet Metal parts and Assemblies
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 125,000
ft2
Annual Production 1,000,000
units
Production Hrs. Annual 4,940
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $276,311 2,285,587
kWh
Electricity Demand $190,968 5,412
kW-mo/yr
Electricity Fees $36,693 -
Natural Gas $44,291 3,254
MMBtu
TOTAL YEARLY COSTS $548,263
RECOMMENDED SAVINGS* $98,325 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $68,168

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $21,900 - $21,900
185,282
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,676 - $10,676
98,436
kWh
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $98 $62 $58
488
kWh
$40
-
kW-mo/yr
- -
04 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $8,159 $6,120 $8,159
69,027
kWh
- - -
05 2.7243: Improve air circulation with destratification fans / other methods $2,182 $2,146 $2,182
18,463
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $52,069 $64,391 $25,412
214,993
kWh
$24,407
-
kW-mo/yr
$1,947 $303
07 2.4239: Eliminate or reduce compressed air usage $3,241 $10,932 $2,365
20,007
kWh
$876
-
kW-mo/yr
- -
TOTAL RECOMMENDED $98,325 $83,651 $70,752
606,696
kWh
$25,323
-
kW-mo/yr
$1,947 $303
TOTAL IMPLEMENTED $68,168 $77,469 $40,635
351,899
kWh
$25,283
-
kW-mo/yr
$1,947 $303
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs