Assessment Year | 2021 |
---|---|
Principal Product | Sheet Metal parts and Assemblies |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
125,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $276,311 | 2,285,587 |
kWh
|
$0.12 |
Electricity Demand | $190,968 | 5,412 |
kW-mo/yr
|
$35.29 |
Electricity Fees | $36,693 | - |
|
- |
Natural Gas | $44,291 | 3,254 |
MMBtu
|
$13.61 |
TOTAL YEARLY COSTS | $548,263 | |||
RECOMMENDED SAVINGS* | $98,325 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,168 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $21,900 | - |
$21,900
185,282
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,676 | - |
$10,676
98,436
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $98 | $62 |
$58
488
kWh
|
$40
-
kW-mo/yr
|
- | - | |
04 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $8,159 | $6,120 |
$8,159
69,027
kWh
|
- | - | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $2,182 | $2,146 |
$2,182
18,463
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52,069 | $64,391 |
$25,412
214,993
kWh
|
$24,407
-
kW-mo/yr
|
$1,947 | $303 | |
07 | 2.4239: Eliminate or reduce compressed air usage | $3,241 | $10,932 |
$2,365
20,007
kWh
|
$876
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $98,325 | $83,651 |
$70,752
606,696
kWh
|
$25,323
-
kW-mo/yr
|
$1,947 | $303 | ||
TOTAL IMPLEMENTED | $68,168 | $77,469 |
$40,635
351,899
kWh
|
$25,283
-
kW-mo/yr
|
$1,947 | $303 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs