ITAC Assessment: SF0558
ITAC logo
ITAC Assessment: SF0558
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Potato Chips, Corn Chips, and Similar Snacks
NAICS 311919: Other Snack Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range greater than $500
M
# of Employees 1,000
Plant Area 540,000
ft2
Annual Production 165,924,726
lb
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,829,947 27,273,502
kWh
Electricity Demand $842,282 49,752
kW-mo/yr
Electricity Fees $264,115 -
Natural Gas $3,521,406 497,693
MMBtu
Waste Disposal Costs
Water Usage $56,000 2,800
Tgal
TOTAL YEARLY COSTS $6,513,750
RECOMMENDED SAVINGS* $162,061 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $118,378

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,941 - $5,781
86,155
kWh
- - $(-840.0)
02 2.3321: Use steam pressure reduction to generate power $98,999 $34,416 - - $98,999
-
MMBtu
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,186 $525 $1,186
17,681
kWh
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,252 $4,542 $9,252
137,880
kWh
- - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,759 $2,995 $4,759
70,928
kWh
- - -
06 2.2511: Insulate bare equipment $282 $379 - - $282
-
MMBtu
-
07 2.1243: Use heat from boiler blowdown to preheat boiler feed water $30,342 $50,211 - - $30,342
-
MMBtu
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,149 $6,701 $3,149
46,925
kWh
- - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $145 $591 $145
2,157
kWh
- - -
10 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $9,006 $75,000 $9,857
146,895
kWh
$3,407
-
kW-mo/yr
$(-4,258.0)
-
MMBtu
-
TOTAL RECOMMENDED $162,061 $175,360 $34,129
508,621
kWh
$3,407
-
kW-mo/yr
$125,365
-
MMBtu
$(-840.0)
TOTAL IMPLEMENTED $118,378 $42,923 $19,937
297,120
kWh
- $99,281
-
MMBtu
$(-840.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs