Assessment Year | 2020 |
---|---|
Principal Product | In-shell Almonds, Raw Almonds, Almond Oil and Almond Powder |
NAICS | 311911: Roasted Nuts and Peanut Butter Manufacturing |
SIC | 2068: Salted and Roasted Nuts and Seeds |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
100,000
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 4,480
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $139,741 | 1,347,499 |
kWh
|
$0.10 | |
Electricity Demand | $125,510 | 5,628 |
kW-mo/yr
|
$22.30 | |
Natural Gas | $4,017 | 280 |
MMBtu
|
$14.35 | |
Waste Disposal Costs | |||||
Water Usage | $20,000 | 1,000 |
Tgal
|
$20.00 | |
TOTAL YEARLY COSTS | $289,268 | ||||
RECOMMENDED SAVINGS* | $146,492 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $111,131 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $25,284 | - | - |
$25,284
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,516 | - |
$4,596
44,324
kWh
|
- | - | $(-1,080.0) | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $575 | $137 |
$95
915
kWh
|
$480
-
kW-mo/yr
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $896 | $400 |
$896
6,282
kWh
|
- | - | - | - | |
05 | 2.3132: Recharge batteries on during off-peak demand periods | $2,065 | $1,862 | - |
$2,065
-
kW-mo/yr
|
- | - | - | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $10,077 | $12,392 |
$7,225
69,677
kWh
|
$7,111
-
kW-mo/yr
|
$(-4,259.0)
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,621 | $33,085 |
$6,878
66,034
kWh
|
$5,712
-
kW-mo/yr
|
- | $739 | $2,292 | |
08 | 2.9114: Use solar heat to make electricty | $88,458 | $451,750 |
$58,025
559,550
kWh
|
$30,433
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $146,492 | $499,626 |
$77,715
746,782
kWh
|
$71,085
-
kW-mo/yr
|
$(-4,259.0)
-
MMBtu
|
$(-341.0) | $2,292 | ||
TOTAL IMPLEMENTED | $111,131 | $487,234 |
$70,490
677,105
kWh
|
$38,690
-
kW-mo/yr
|
- | $(-341.0) | $2,292 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs