ITAC Assessment: SF0525
ITAC logo
ITAC Assessment: SF0525
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Structural Steel
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 283,000
ft2
Annual Production 5,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $245,655 1,098,760
kWh
Electricity Fees $31,644 -
Natural Gas $7,091 481
MMBtu
TOTAL YEARLY COSTS $284,390
RECOMMENDED SAVINGS* $256,176 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $128,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $49,766 - $49,766
197,193
kWh
- - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,260 - $17,220
68,238
kWh
- - $(-960.0) - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,078 $160 $2,078
8,232
kWh
- - - - -
04 2.7224: Reduce space conditioning during non-working hours $3,086 $354 $80
315
kWh
- $3,006
-
MMBtu
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $60,368 $59,620 $57,443
227,614
kWh
- - $2,190 - $735
06 2.9114: Use solar heat to make electricty $124,618 $491,526 $115,232
456,598
kWh
$8,498 - - $888 -
TOTAL RECOMMENDED $256,176 $551,660 $241,819
958,190
kWh
$8,498 $3,006
-
MMBtu
$1,230 $888 $735
TOTAL IMPLEMENTED $128,472 $59,780 $126,507
501,277
kWh
- - $1,230 - $735
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs