| Assessment Year | 2025 |
|---|---|
| Principal Product | Wastewater Treatment Facility |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 5 |
| Plant Area |
27,000
ft2
|
| Annual Production | 300,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $56,686 | 969,201 |
kWh
|
$0.058 | |
| Electricity Demand | $20,922 | 1,772 |
kW-mo/yr
|
$11.81 | |
| Electricity Fees | $1,004 | - |
|
- | |
| Natural Gas | $15,811 | 2,034 |
MMBtu
|
$7.77 | |
| Other Gas | $1,680 | 1 |
MMBtu
|
$1,680.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $34,869 | 5,312 |
Tgal
|
$6.56 | |
| TOTAL YEARLY COSTS | $130,972 | ||||
| RECOMMENDED SAVINGS* | $28,939 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4151: Minimize water usage | $25,065 | $53,711 |
$(-257.0)
(-4,440)
kWh
|
$(-211.0)
-
kW-mo/yr
|
- |
$25,533
-
Tgal
|
|
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,553 | - | - | - |
$3,553
-
MMBtu
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $107 | - |
$84
1,441
kWh
|
$23
-
kW-mo/yr
|
- | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $181 | $1,899 |
$140
2,419
kWh
|
$41
-
kW-mo/yr
|
- | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $33 | $120 | - | - |
$33
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $28,939 | $55,730 |
$(-33.1)
(-580)
kWh
|
$(-146.9)
-
kW-mo/yr
|
$3,586
-
MMBtu
|
$25,533
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs