Assessment Year | 2018 |
---|---|
Principal Product | Wine |
NAICS | 312130: Wineries |
SIC | 2084: Wines, Brandy, and Brandy Spirits |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
195,377
ft2
|
Annual Production | 1,200
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $322,399 | 3,050,371 |
kWh
|
$0.11 |
Electricity Demand | $239,739 | 7,776 |
kW-mo/yr
|
$30.83 |
Natural Gas | $68,720 | 7,076 |
MMBtu
|
$9.71 |
TOTAL YEARLY COSTS | $630,859 | |||
RECOMMENDED SAVINGS* | $79,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,062 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $8,926 | - |
$8,926
84,459
kWh
|
- | - | - | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $412 | - |
$222
2,105
kWh
|
$190
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $7,541 | $798 |
$124
1,171
kWh
|
- |
$7,417
-
MMBtu
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,704 | $208 |
$1,094
10,351
kWh
|
$610
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $463 | $378 | - | - |
$463
-
MMBtu
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,866 | $17,240 |
$8,667
82,006
kWh
|
$2,909
-
kW-mo/yr
|
- | $337 | $(-47.0) | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,992 | $9,121 |
$2,297
21,734
kWh
|
$695
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2628: Utilize a less expensive cooling method | $6,328 | $27,411 |
$6,328
59,874
kWh
|
- | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,150 | - | - | - | - | $(-1,887.0) | - | $12,037 | |
10 | 4.212: Adopt in-house material generation | $29,406 | $113,992 | - | - | - | - | $29,406 | - | |
TOTAL RECOMMENDED | $79,788 | $169,148 |
$27,658
261,700
kWh
|
$4,404
-
kW-mo/yr
|
$7,880
-
MMBtu
|
$(-1,550.0) | $29,359 | $12,037 | ||
TOTAL IMPLEMENTED | $41,062 | $18,624 |
$19,033
180,092
kWh
|
$3,709
-
kW-mo/yr
|
$7,880
-
MMBtu
|
$(-1,550.0) | $(-47.0) | $12,037 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs