ITAC Assessment: SF0524
ITAC logo
ITAC Assessment: SF0524
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Wine
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 195,377
ft2
Annual Production 1,200
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $322,399 3,050,371
kWh
Electricity Demand $239,739 7,776
kW-mo/yr
Natural Gas $68,720 7,076
MMBtu
TOTAL YEARLY COSTS $630,859
RECOMMENDED SAVINGS* $79,788 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,062

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings By-product Production Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $8,926 - $8,926
84,459
kWh
- - - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $412 - $222
2,105
kWh
$190
-
kW-mo/yr
- - - -
03 2.7224: Reduce space conditioning during non-working hours $7,541 $798 $124
1,171
kWh
- $7,417
-
MMBtu
- - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,704 $208 $1,094
10,351
kWh
$610
-
kW-mo/yr
- - - -
05 2.2511: Insulate bare equipment $463 $378 - - $463
-
MMBtu
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $11,866 $17,240 $8,667
82,006
kWh
$2,909
-
kW-mo/yr
- $337 $(-47.0) -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,992 $9,121 $2,297
21,734
kWh
$695
-
kW-mo/yr
- - - -
08 2.2628: Utilize a less expensive cooling method $6,328 $27,411 $6,328
59,874
kWh
- - - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,150 - - - - $(-1,887.0) - $12,037
10 4.212: Adopt in-house material generation $29,406 $113,992 - - - - $29,406 -
TOTAL RECOMMENDED $79,788 $169,148 $27,658
261,700
kWh
$4,404
-
kW-mo/yr
$7,880
-
MMBtu
$(-1,550.0) $29,359 $12,037
TOTAL IMPLEMENTED $41,062 $18,624 $19,033
180,092
kWh
$3,709
-
kW-mo/yr
$7,880
-
MMBtu
$(-1,550.0) $(-47.0) $12,037
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs