Assessment Year | 2018 |
---|---|
Principal Product | Food Pudding |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 107 |
Plant Area |
78,000
ft2
|
Annual Production | 30,500,000
lb
|
Production Hrs. Annual | 6,660
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $294,094 | 3,103,238 |
kWh
|
$0.095 |
Electricity Demand | $97,754 | 8,626 |
kW-mo/yr
|
$11.33 |
Natural Gas | $109,465 | 11,484 |
MMBtu
|
$9.53 |
TOTAL YEARLY COSTS | $501,313 | |||
RECOMMENDED SAVINGS* | $130,136 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,149 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6214: Shut off pilots in standby equipment | $3,418 | $136 |
$55
580
kWh
|
- |
$3,363
-
MMBtu
|
- | - | |
02 | 2.2694: Use highest temperature for chilling or cold storage | $7,652 | $800 |
$6,575
69,382
kWh
|
$1,077
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,563 | $136 |
$2,136
22,540
kWh
|
$427
-
kW-mo/yr
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $4,469 | $4,039 | - | - |
$4,469
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,296 | $8,179 |
$6,843
72,212
kWh
|
$1,797
-
kW-mo/yr
|
- | $188 | $(-532.0) | |
06 | 2.7135: Install occupancy sensors | $942 | $900 |
$942
9,944
kWh
|
- | - | - | - | |
07 | 2.2621: Modify refrigeration system to operate at a lower pressure | $17,938 | $24,858 |
$17,938
189,277
kWh
|
- | - | - | - | |
08 | 2.9114: Use solar heat to make electricty | $82,569 | $631,513 |
$74,168
782,612
kWh
|
$8,401
-
kW-mo/yr
|
- | - | - | |
09 | 2.3132: Recharge batteries on during off-peak demand periods | $2,289 | $953 | - |
$2,289
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $130,136 | $671,514 |
$108,657
1,146,547
kWh
|
$13,991
-
kW-mo/yr
|
$7,832
-
MMBtu
|
$188 | $(-532.0) | ||
TOTAL IMPLEMENTED | $44,149 | $39,865 |
$34,434
363,355
kWh
|
$5,590
-
kW-mo/yr
|
$4,469
-
MMBtu
|
$188 | $(-532.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs