Assessment Year | 2018 |
---|---|
Principal Product | Glassware |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 14 |
Plant Area |
7,500
ft2
|
Annual Production | 71,000
units
|
Production Hrs. Annual | 8,688
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $20,114 | 119,094 |
kWh
|
$0.17 |
Electricity Demand | $10,504 | 571 |
kW-mo/yr
|
$18.39 |
Natural Gas | $64,644 | 6,431 |
MMBtu
|
$10.05 |
TOTAL YEARLY COSTS | $95,262 | |||
RECOMMENDED SAVINGS* | $49,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $13,874 | $3,023 | - | - |
$13,874
-
MMBtu
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,220 | $4,857 |
$7,471
44,234
kWh
|
$749
-
kW-mo/yr
|
- | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $17,611 | $15,000 | - | - |
$17,611
-
MMBtu
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,777 | $2,300 |
$1,070
6,337
kWh
|
$472
-
kW-mo/yr
|
- | $99 | $136 | |
05 | 2.1122: Re-size charging openings or add a movable door on equipment | $2,098 | $6,325 | - | - |
$2,098
-
MMBtu
|
- | - | |
06 | 2.9114: Use solar heat to make electricty | $6,223 | $45,702 |
$6,223
36,844
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $49,803 | $77,207 |
$14,764
87,415
kWh
|
$1,221
-
kW-mo/yr
|
$33,583
-
MMBtu
|
$99 | $136 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs