ITAC Assessment: SF0515
ITAC logo
ITAC Assessment: SF0515
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product CNC Metal Parts
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 5,800
ft2
Annual Production 75,000
units
Production Hrs. Annual 5,720
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,102 465,868
kWh
Electricity Demand $17,956 1,237
kW-mo/yr
Natural Gas $366 22
MMBtu
TOTAL YEARLY COSTS $92,424
RECOMMENDED SAVINGS* $19,003 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,072

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Primary Raw Material Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $2,061 $80 $2,061
12,959
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,072 $2,241 $830
5,219
kWh
$189
-
kW-mo/yr
$47 $6
03 2.9114: Use solar heat to make electricty $15,870 $84,912 $15,870
99,771
kWh
- - -
TOTAL RECOMMENDED $19,003 $87,233 $18,761
117,949
kWh
$189
-
kW-mo/yr
$47 $6
TOTAL IMPLEMENTED $1,072 $2,241 $830
5,219
kWh
$189
-
kW-mo/yr
$47 $6
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs