| Assessment Year | 2018 |
|---|---|
| Principal Product | CNC Metal Parts |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 20 |
| Plant Area |
5,800
ft2
|
| Annual Production | 75,000
units
|
| Production Hrs. Annual | 5,720
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $74,102 | 465,868 |
kWh
|
$0.16 |
| Electricity Demand | $17,956 | 1,237 |
kW-mo/yr
|
$14.52 |
| Natural Gas | $366 | 22 |
MMBtu
|
$16.41 |
| TOTAL YEARLY COSTS | $92,424 | |||
| RECOMMENDED SAVINGS* | $19,003 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,072 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,061 | $80 |
$2,061
12,959
kWh
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,072 | $2,241 |
$830
5,219
kWh
|
$189
-
kW-mo/yr
|
$47 | $6 | |
| 03 | 2.9114: Use solar heat to make electricty | $15,870 | $84,912 |
$15,870
99,771
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $19,003 | $87,233 |
$18,761
117,949
kWh
|
$189
-
kW-mo/yr
|
$47 | $6 | ||
| TOTAL IMPLEMENTED | $1,072 | $2,241 |
$830
5,219
kWh
|
$189
-
kW-mo/yr
|
$47 | $6 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs