Assessment Year | 2017 |
---|---|
Principal Product | Recycled Packaging |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
50,000
ft2
|
Annual Production | 758,400
units
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $94,534 | 694,523 |
kWh
|
$0.14 | |
Electricity Demand | $56,352 | 3,872 |
kW-mo/yr
|
$14.55 | |
Natural Gas | $4,657 | 374 |
MMBtu
|
$12.44 | |
Waste Disposal Costs | |||||
Water Usage | $14,977 | 1,403,346 |
Tgal
|
$0.011 | |
TOTAL YEARLY COSTS | $170,520 | ||||
RECOMMENDED SAVINGS* | $69,368 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $18,862 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,199 | - |
$1,739
12,736
kWh
|
- | - | $(-540.0) | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $4,566 | $698 |
$983
7,203
kWh
|
- |
$3,583
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,202 | $9,352 |
$5,043
36,945
kWh
|
- | - | $1,257 | $(-98.0) | |
04 | 2.2511: Insulate bare equipment | $118 | $389 | - | - |
$118
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $6,777 | $31,273 |
$3,821
27,994
kWh
|
$1,570
-
kW-mo/yr
|
- | $1,403 | $(-17.0) | |
06 | 2.9114: Use solar heat to make electricty | $50,506 | $343,102 |
$50,506
369,950
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $69,368 | $384,814 |
$62,092
454,828
kWh
|
$1,570
-
kW-mo/yr
|
$3,701
-
MMBtu
|
$2,120 | $(-115.0) | ||
TOTAL IMPLEMENTED | $18,862 | $41,712 |
$11,586
84,878
kWh
|
$1,570
-
kW-mo/yr
|
$3,701
-
MMBtu
|
$2,120 | $(-115.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs