Assessment Year | 2017 |
---|---|
Principal Product | Circuit Board Plating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 28 |
Plant Area |
10,000
ft2
|
Annual Production | 12,000,000
units
|
Production Hrs. Annual | 5,720
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,521 | 784,954 |
kWh
|
$0.15 |
Electricity Demand | $50,846 | 1,815 |
kW-mo/yr
|
$28.01 |
Natural Gas | $14,196 | 1,247 |
MMBtu
|
$11.38 |
TOTAL YEARLY COSTS | $185,563 | |||
RECOMMENDED SAVINGS* | $9,993 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,993 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $2,043 | - |
$3,291
21,431
kWh
|
- | - | $(-1,248.0) | - | |
02 | 2.7314: Reduce ventilation air | $1,680 | - |
$1,116
7,266
kWh
|
$564
-
kW-mo/yr
|
- | - | - | |
03 | 2.2514: Cover open tanks | $2,660 | $1,059 |
$2,660
17,322
kWh
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $824 | $1,526 | - | - |
$824
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,786 | $5,219 |
$2,101
13,682
kWh
|
$171
-
kW-mo/yr
|
- | - | $514 | |
TOTAL RECOMMENDED | $9,993 | $7,804 |
$9,168
59,701
kWh
|
$735
-
kW-mo/yr
|
$824
-
MMBtu
|
$(-1,248.0) | $514 | ||
TOTAL IMPLEMENTED | $9,993 | $7,804 |
$9,168
59,701
kWh
|
$735
-
kW-mo/yr
|
$824
-
MMBtu
|
$(-1,248.0) | $514 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs