Assessment Year | 2016 |
---|---|
Principal Product | Wine |
NAICS | 312130: Wineries |
SIC | 2084: Wines, Brandy, and Brandy Spirits |
Sales Range | $5 M to 10M |
# of Employees | 11 |
Plant Area |
60,000
ft2
|
Annual Production | 630
Tgal
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,768 | 418,691 |
kWh
|
$0.14 |
Electricity Demand | $35,974 | 2,426 |
kW-mo/yr
|
$14.83 |
Natural Gas | $14,340 | 1,627 |
MMBtu
|
$8.82 |
TOTAL YEARLY COSTS | $109,082 | |||
RECOMMENDED SAVINGS* | $63,557 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,064 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3132: Recharge batteries on during off-peak demand periods | $2,238 | - | - | - | $2,238 | - | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $270 | - |
$340
2,425
kWh
|
- | - | - | $(-70.0) | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $5,772 | $2,510 |
$2,923
20,825
kWh
|
- | - |
$2,849
-
MMBtu
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,469 | $4,948 |
$1,362
9,702
kWh
|
$846
-
kW-mo/yr
|
- | - | - | $137 | $124 | |
05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,493 | $5,050 |
$1,493
10,635
kWh
|
- | - | - | - | - | - | |
06 | 2.7135: Install occupancy sensors | $567 | $2,381 |
$309
2,201
kWh
|
$258
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.9114: Use solar heat to make electricty | $50,748 | $406,834 |
$36,734
261,715
kWh
|
$14,014
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $63,557 | $421,723 |
$43,161
307,503
kWh
|
$15,118
-
kW-mo/yr
|
$2,238 |
$2,849
-
MMBtu
|
$(-70.0) | $137 | $124 | ||
TOTAL IMPLEMENTED | $62,064 | $416,673 |
$41,668
296,868
kWh
|
$15,118
-
kW-mo/yr
|
$2,238 |
$2,849
-
MMBtu
|
$(-70.0) | $137 | $124 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs