Assessment Year | 2014 |
---|---|
Principal Product | Transformers |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
105,400
ft2
|
Annual Production | 84
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $397,257 | 3,328,517 |
kWh
|
$0.12 |
Electricity Demand | $229,436 | 9,480 |
kW-mo/yr
|
$24.20 |
Electricity Fees | $6,713 | - |
|
- |
Natural Gas | $21,317 | 2,227 |
MMBtu
|
$9.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $164,526 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,318 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $6,081 | - |
$6,081
65,015
kWh
|
- | - | - | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $1,343 | - |
$1,343
12,617
kWh
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,894 | $68,183 |
$24,384
229,042
kWh
|
$10,493
-
kW-mo/yr
|
- | - | $(-1,983.0) | |
04 | 2.7134: Use photocell controls | $5,656 | $20,482 |
$3,573
33,561
kWh
|
$2,083
-
kW-mo/yr
|
- | - | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $22,823 | - | - | - | $22,823 | - | - | |
06 | 2.3511: Use plant owned transformers or lease transformers | $67,626 | $187,500 | - | - | $67,626 | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $28,103 | $27,500 | - | - | - | $28,103 | - | |
TOTAL RECOMMENDED | $164,526 | $303,665 |
$35,381
340,235
kWh
|
$12,576
-
kW-mo/yr
|
$90,449 | $28,103 | $(-1,983.0) | ||
TOTAL IMPLEMENTED | $40,318 | $68,183 |
$31,808
306,674
kWh
|
$10,493
-
kW-mo/yr
|
- | - | $(-1,983.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs