ITAC Assessment: SF0452
ITAC logo
ITAC Assessment: SF0452
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Treated wastewater
NAICS 221310: Water Supply and Irrigation Systems
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 7
Plant Area 348,480
ft2
Annual Production 331,066
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $212,348 2,705,248
kWh
Electricity Demand $29,490 4,396
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $69,652 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,968

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 3.7141: Improve cleaning efficiency by maintaining cleaning system $13,134 $1,372 $11,757
149,796
kWh
$1,377
-
kW-mo/yr
-
02 2.7224: Reduce space conditioning during non-working hours $1,312 $552 $950
12,106
kWh
- $362
-
MMBtu
03 2.4322: Use or replace with energy efficient substitutes $27,969 $47,618 $25,037
318,986
kWh
$2,932
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,986 $6,681 $1,778
22,650
kWh
$208
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,913 $23,541 $4,398
56,030
kWh
$515
-
kW-mo/yr
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $536 $2,722 $480
6,110
kWh
$56
-
kW-mo/yr
-
07 2.4322: Use or replace with energy efficient substitutes $19,802 $104,674 $17,726
225,843
kWh
$2,076
-
kW-mo/yr
-
TOTAL RECOMMENDED $69,652 $187,160 $62,126
791,521
kWh
$7,164
-
kW-mo/yr
$362
-
MMBtu
TOTAL IMPLEMENTED $16,968 $11,327 $14,965
190,662
kWh
$1,641
-
kW-mo/yr
$362
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs