ITAC Assessment: SF0449
ITAC logo
ITAC Assessment: SF0449
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Ophthalmic Equipment
NAICS 333314: Optical Instrument and Lens Manufacturing
SIC 3827: Optical Instruments and Lenses
Sales Range $10
M
to 50
M
# of Employees 720
Plant Area 200,000
ft2
Annual Production 5
units
Production Hrs. Annual 2,600
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $188,873 2,524,403
kWh
Electricity Demand $104,412 5,851
kW-mo/yr
Natural Gas $20,517 2,317
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $56,008 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,290

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7144: Install spectral reflectors / delamp $660 $280 $398
3,177
kWh
$262
-
kW-mo/yr
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,804 $9,262 $3,549
28,314
kWh
$8,354
-
kW-mo/yr
$(-1,099.0)
03 2.6211: Conserve energy by efficient use of vending machines $317 $307 $317
2,529
kWh
- -
04 2.7226: Use computer programs to optimize hvac performance $28,600 $42,672 $18,248
145,564
kWh
$10,352
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $12,630 $27,842 $3,274
26,114
kWh
- $9,356
06 2.7135: Install occupancy sensors $2,997 $14,024 $1,819
14,511
kWh
$1,178
-
kW-mo/yr
-
TOTAL RECOMMENDED $56,008 $94,387 $27,605
220,209
kWh
$20,146
-
kW-mo/yr
$8,257
TOTAL IMPLEMENTED $13,290 $28,122 $3,672
29,291
kWh
$262
-
kW-mo/yr
$9,356
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs