| Assessment Year | 2014 |
|---|---|
| Principal Product | Peptides |
| NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
| SIC | 2836: Biological Products, Except Diagnostic Substances |
| Sales Range | $10 M to 50M |
| # of Employees | 44 |
| Plant Area |
130,000
ft2
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $77,715 | 880,560 |
kWh
|
$0.088 |
| Electricity Demand | $47,304 | 2,003 |
kW-mo/yr
|
$23.62 |
| Natural Gas | $7,618 | 775 |
MMBtu
|
$9.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,198 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $2,021 | - |
$489
5,541
kWh
|
- |
$1,532
-
MMBtu
|
|
| 02 | 2.6218: Turn off equipment when not in use | $4,864 | $2,722 |
$4,607
52,200
kWh
|
- |
$257
-
MMBtu
|
|
| 03 | 2.7131: Add area lighting switches | $409 | $252 |
$179
2,023
kWh
|
$230
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,082 | $12,459 |
$1,299
14,721
kWh
|
$1,783
-
kW-mo/yr
|
- | |
| 05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $231 | $1,559 |
$169
1,909
kWh
|
$62
-
kW-mo/yr
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $14,162 | $173,094 |
$7,563
76,222
kWh
|
$6,599
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $24,769 | $190,086 |
$14,306
152,616
kWh
|
$8,674
-
kW-mo/yr
|
$1,789
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,198 | $16,740 |
$6,564
74,371
kWh
|
$1,845
-
kW-mo/yr
|
$1,789
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs