ITAC Assessment: SF0435
ITAC logo
ITAC Assessment: SF0435
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product treated water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 11
Plant Area 909,098
ft2
Annual Production 1,277,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $448,795 5,377,218
kWh
Electricity Demand $210,270 9,852
kW-mo/yr
Electricity Fees $5,601 -
Natural Gas $1,200 126
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $451,542 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $451,542

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7135: Install occupancy sensors $12,509 $9,202 $8,130
97,365
kWh
$4,379
-
kW-mo/yr
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,788 $6,238 $5,321
63,723
kWh
$3,467
-
kW-mo/yr
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,176 $15,794 $6,060
72,571
kWh
$2,116
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $192,884 $831,276 $142,971
1,712,228
kWh
$49,913
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,287 $44,123 $2,885
34,552
kWh
$1,066
-
kW-mo/yr
- $837 $499
06 2.9114: Use solar heat to make electricty $209,686 $1,399,178 $180,342
2,141,217
kWh
$29,344
-
kW-mo/yr
- - -
07 3.1191: Change procedures / equipment / operating conditions $14,212 - - - $14,212 - -
TOTAL RECOMMENDED $451,542 $2,305,811 $345,709
4,121,656
kWh
$90,285
-
kW-mo/yr
$14,212 $837 $499
TOTAL IMPLEMENTED $451,542 $2,305,811 $345,709
4,121,656
kWh
$90,285
-
kW-mo/yr
$14,212 $837 $499
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs